A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements : 1. The work will be finished on Thursday. 2. The work will be finished in 10 days. Which of the above statements is/are correct?

  • 1 only
  • 2 only
  • Both 1 and 2
  • Neither 1 nor 2